In a PERT network, the optimistic time for a particular activity is 9 weeks, and the pessimistic time is 21 weeks. Which one of the following is the best estimate of the standard deviation for the activity ?
a) 12
b) 6
c) 2
d) 9
The answer eludes me. If you know the answer then post away!